Fort Peck Dam
The Fort Peck Dam is the highest of six major dams along the Missouri River, located in northeast Montana in the United States, near Glasgow, and adjacent to the community of Fort Peck. At 21,026 feet (6,409 metres) in length and over 250 feet (76 metres) in height, it is the largest hydraulically filled dam in the United States, and creates Fort Peck Lake, the fifth largest man-made lake in the U.S. It lies within the Charles M. Russell National Wildlife Refuge. The dam and 134-mile (216 km) long lake exist for the purposes of hydroelectric power generation, flood control, and water quality management.[1]
The dam presently has a nameplate capacity of 185,250 kilowatts, divided among 5 generating units. Three units in powerhouse number one, completed in 1951, generate a total of 105,000 kilowatts. Completed in 1961, the two remaining generating units in powerhouse number 2, have a nameplate capacity of 80,000 kilowatts.[2]
The lake has a maximum operating pool elevation of 2,250 feet (690 metres) above mean sea level and a normal operating pool elevation of 2,246 (685 m) above mean sea level.[3] The lake level fluctuates over time based on a number of factors. During the first week of February 2007, the reservoir set a record low elevation of 2,197 feet (670 metres) above mean sea level, nearly 12 feet lower than the previous record low set in 1991.[4][5]
History
Fort Peck is a product of U.S. President Franklin D. Roosevelt's New Deal. Construction of Fort Peck Dam started in 1933, and at its peak in July 1936 employed 10,546 workers. The dam, named for a 19th-century trading post, was completed in 1940, and began generating electricity in July 1943. The town of Fort Peck, Montana, "the government town," was built for Army Corps of Engineers personnel and men in "positions of responsibility" and their families during the dam's construction. Many of the facilities that supported the dam's workers are still utilized today, such as the recreation center and the theater. In addition to Fort Peck, other towns sprang up to house the workers. Among these were Wheeler and McCone City as well as more than a dozen others. Many of the homes were later moved to farms and towns around Montana.
Dam failure during construction
The site chosen was on a stretch of the Missouri River flowing from south to north. The river bed at the site consisted of approximately 160 feet (49 metres) of alluvial deposits, varying from coarse, pervious sands and gravels to impermeable clays. Beneath these deposits lay a thick (approximately 1,000 feet (300 m)) deposit of Bear Paw shale. This shale is classified as a firm shale and contains thin (<1 to 6 in (2.5 to 15.2 cm) layers of bentonite. The topmost layer of soft clay was removed from the alluvium in order to found the dam on the stable sandy deposits beneath, at an elevation of approximately 2,050 feet (620 metres). The remaining deposits consisted of the alluvial materials mentioned above. These deposits had many interconnecting layers of coarse sands and gravels, necessitating the installation of a steel sheet pile wall down to the firm shale, from the left to the right abutment.
The dam was planned to extend to an elevation of 2,275 feet (693 m), for a total height of 225 feet (69 m) from the cleared river bed and had a length from the left to the right abutment of approximately 10,500 feet (3,200 m). The upstream face was designed with an average slope of one vertical on four horizontal and included three horizontal shelves built into the slope. A flatter (1 on 7.5) berm was to be placed between stations 30+00 and 75+00 (approximately the center half of the length of the dam).
Since the construction method of hydraulic fill was chosen, four electric dredges needed to be built. Due to the distance of the site from the nearest shoreline, a shipyard was started on the site, affectionately dubbed “The Fort Peck Navy” and “The Biggest Shipyard in Montana” by the workers. These dredges would pump material from nearby borrow pits to the dam site where it was discharged by pipes along the outside edges of the fill. The coarser material settled out quickly, while the fines were carried downhill toward what would eventually become the core of the dam. Samples were take from all zones regularly to ensure that the material had the gradation and consolidation characteristics specified by the design.
This process proceeded until elevation of the fill reached approximately 2250 ft (686 metres (2,251 ft) (61 m) above the foundation), while the reservoir was at an elevation of 2,117.5 feet (645.4 metres). At this point, the danger of the core pool overtopping or bursting the shell became greater because the beaches became narrower. For this reason, an extensive alarm system was implemented along the narrower upstream shell. This alarm system could immediately shut off the dredge pumps if a shell breach was detected. Part of this alarm system involved monitoring the elevations of the core pool and the pipelines carrying the dredged fill.
On the morning of September 22, 1938, an inspection by the engineer in charge of construction revealed that the elevation of the pipeline relative to the core pool near station 15+10 (see attached overhead photo) was only 2.5 feet (0.76 m) when it should have been 4.5 feet (1.4 m). A survey crew was dispatched immediately to determine if the fill on which the pipeline was founded was settling or if the pipeline footing itself was settling. Preliminary measurement showed that the pipeline was closer to the pool than expected from station 15+00 to station 17+00. A meeting with the district engineer and supervisory personnel was scheduled for 1:15 p.m. near the location in question.
At approximately 1:15 p.m. the core pool near station 15+00 began to settle slowly. As its rate of settlement increased, cracks appeared 30 feet (9.1 metres) below the crest in the upstream embankment. As the settlement of the pool got larger, portions of the shell began to slide backwards into the core pool area and the majority of the upstream shell began to move into the reservoir, translating south and rotating slightly about the east abutment. The west end of the slide mass broke away from the dam near station 27+00 and the core pool water rapidly poured out of the breach that was created in the shell. Portions of the core in the still-stable portion of the dam continued to slump into the hole created by the loss of the slide mass. One construction supervisor was backing his car away from the advancing scarp to the west along the beach to avoid the slumping and noted that the small scarp in the core was advancing to the west at a speed equal to his own (approximately 10 mph (16 km/h)).
A pump barge moored near the dam at the east abutment was swamped by the slide and was lost along with several tractors, loadmasters, and draglines on the slope. Of the 134 men working in the area at the time, 34 were carried into the sliding material. Of these 34, eight were unable to be rescued and lost their lives. Of these 8 men, only 2 bodies were ever recovered, leaving 6 men permanently entombed in the structure.
In the testing and analysis done by the Corps of Engineers and others to determine the cause of the slide, several modes of failure were considered. These were: movement along a weak zone in the shale in the abutment, movement along the shale surface, bursting of the shell due to excessive core pressure, and temporary liquefaction of the shell or foundation sand. Extensive laboratory testing of the shale, both weathered and unweathered indicated strengths leading to a factor of safety greater than one. Also, portions of the weathered shale were found in the slide mass, indicating that the slip surface was located somewhere in the shale, but probably at a shallow depth. The core material turned out to be much stronger than expected (having a friction angle of approximately 29 degrees) and was carried out into the slide nearly in a solid mass, making it unlikely that the core was the weak point in the slide. Laboratory testing was done on the shell material and the foundation sand and it was determined that both materials were denser than the critical state for liquefaction. There was no evidence of ground vibration, seismic or otherwise. Some liquefaction may have occurred after the sliding was initiated, but it was unlikely that it caused the slide.
The major weak point in the dam seemed to be the bentonite seams in the Bear Paw shale. Very high water pressures were reported at some points in the shale during the construction. This was likely caused by consolidation due to the overburden of the fill being placed for the dam. The excess pore pressures could not be relieved due to the low permeability of the surrounding shale. This resulted in a low effective stress in the bentonite and a very low shear strength.
Representations in art and literature
Fort Peck Dam is probably best known for being the subject of a photograph of the spillway taken by Margaret Bourke-White while still under construction that was the cover photo of the first issue of Life magazine on November 23, 1936. Later, the photograph by Bourke-White was used on a United States postage stamp in the "Celebrate the Century" series.
The dam is also center-stage in Bucking the Sun, by the Montana-born writer Ivan Doig, published in 1996. The novel tells the story of the fictional Duff family and their various roles in the mammoth dam project, and in the process describes the working conditions and way of life of the thousands of workers hired to construct the Fort Peck Dam, many of them homesteaders from upriver farms destined to disappear under the waters of the newly formed Fort Peck Lake.
Fifty Cents an Hour: The Builders and Boomtowns of the Fort Peck Dam, by Montana author Lois Lonnquist, published in 2006, is an overall history of the Fort Peck dam and spillway construction. Built by the Army Corps of Engineers, PWA Project #30 provided thousands of jobs during the Great Depression. The book includes the history of the boomtowns that sprang up in the area, and the "project people" who lived and worked at Fort Peck during the "dam days."
Notes and References
- ^ "Fort peck Project". U.S. Army Corps of Engineers. Retrieved 2007-02-09.
- ^ "Fort Peck Dam and Power Plant". US Army Corps of Engineers. Retrieved 2007-02-09.
- ^ "Summary of Engineering Data - Missouri River Main Stem Reservoirs" (PDF). Missouri River Division, Corps of Engineers, U.S. Army. 2001. Retrieved 2007-02-10.
{{cite web}}
: Unknown parameter|month=
ignored (help) - ^ "Across the Big Sky: Reservoir low water level sets record". Great Falls Tribune. 2007-02-10. Retrieved 2007-02-10.
- ^ "Missouri River Region Daily River Bulletin". U.S. Army Corps of Engineers. 2007-02-10. Retrieved 2007-02-10.
- Middlebrooks, T. A. (1942), “Fort Peck Slide,” Transactions of the American Society of Civil Engineers, 107, 723-764
- “Report on the Slide of a Portion of the Upstream Face of the Fort Peck Dam” (1939), Corps of Engineers, US Army.
Further reading
- Doig, Ivan (1996) Bucking the Sun, New York: Simon and Schuster, Inc. ISBN 0-684-81171-5
- Lonnquist, Lois (2006) Fifty Cents an Hour: The Builders and Boomtowns of the Fort Peck Dam, MtSky Press ISBN 0-9786963-0-1
External links
- Fort Peck Project website - U.S. Army Corps of Engineers
- Fort Peck Dam, unofficial website
- Life Magazine construction photos