The second test flight was originally scheduled for January 2007, but was delayed because of problems with the second stage. Before the January launch date, SpaceX had stated earlier potential launch dates, moving from September 2006 to November and December. In December the launch was rescheduled for 9 March, but delayed because of range availability issues caused by a [[Minuteman III]] test flight, which would re-enter over Kwajelein. The launch attempt on 19 March was delayed 45 minutes from 23:00 GMT because of a data-relay issue, and then scrubbed 1 minute 2 seconds before launch at 23:45 because of a computer issue, whereby the safety computer incorrectly detected a transmission failure caused by a hardware delay of a few [[millisecond]]s in the process. 20 March attempt was delayed 65 minutes from an originally planned time of 23:00 because of a problem with communications between one of the NASA experiments in the payload and the [[TDRS]] system. |
The second test flight was originally scheduled for January 2007, but was delayed because of problems with the second stage. Before the January launch date, SpaceX had stated earlier potential launch dates, moving from September 2006 to November and December. In December the launch was rescheduled for 9 March, but delayed because of range availability issues caused by a [[Minuteman III]] test flight, which would re-enter over Kwajelein. The launch attempt on 19 March was delayed 45 minutes from 23:00 GMT because of a data-relay issue, and then scrubbed 1 minute 2 seconds before launch at 23:45 because of a computer issue, whereby the safety computer incorrectly detected a transmission failure caused by a hardware delay of a few [[millisecond]]s in the process. 20 March attempt was delayed 65 minutes from an originally planned time of 23:00 because of a problem with communications between one of the NASA experiments in the payload and the [[TDRS]] system. |
||
The first launch attempt on 21 March 2007 was aborted at 00:05 GMT at the last second before launch and after the engine had ignited. It was, however, decided that another launch should be made the same day. The rocket successfully left the launch pad at 01:10 GMT on 21 March 2007 with a [[DemoSat]] payload for [[DARPA]] and [[NASA]]. The rocket performed well during the first-stage burn. However, during staging, the interstage fairing on the top of the first stage bumped the second-stage engine bell.<ref>{{cite web |url=http://www.spacedaily.com/reports/SpaceX_Confirms_Stage_Bump_On_Demoflight_2_999.html |title=SpaceX Confirms Stage Bump On Demoflight 2 |date=23 March 2007 |author=Greg Zsidisin |publisher=Space Daily |access-date=24 June 2017 }}</ref> The bump occurred as the second-stage nozzle exited the interstage, with the first stage rotating much faster than expected (a rotation rate of about 2.5°/s vs. expected rate of 0.5°/s maximum), thereby making contact with the [[niobium]] nozzle of the second stage. Elon Musk reported that the bump did not appear to have caused damage, and that the reason why they chose a niobium skirt instead of [[Reinforced carbon–carbon|carbon–carbon]] was to prevent problematic damage in the event of such incidents. Shortly after second-stage ignition, a stabilization ring detached from the engine bell as designed.<ref name="falconf2status">{{cite news |url=http://www.spaceflightnow.com/falcon/f2/status.html |title=Mission Status Center |date=20 March 2007 |publisher=Space Flight Now }}</ref> At around T+4:20, a circular coning oscillation began, which increased in amplitude until video was lost. At T+5:01, the vehicle started to roll, and telemetry ended. According to [[Elon Musk]], the second-stage engine shut down at T+7:30 because of a roll-control issue. Sloshing of propellant in the LOX tank increased oscillation. This oscillation would normally have been dampened by the Thrust Vector Control system in the second stage, but the bump to the second nozzle during separation caused an overcompensation in the correction.<ref name="falconf2status"/> The rocket continued to within one minute of its desired location and also managed to deploy the satellite mass-simulator ring. While the webcast video ended prematurely, SpaceX was able to retrieve telemetry for the entire flight.<ref>{{cite web |url=https://www.nasaspaceflight.com/2007/03/falcon-i-flight-preliminary-assessment-positive-for-spacex/ |title=Falcon I flight – preliminary assessment positive for SpaceX |date=24 March 2007 |author=Chris Bergin |publisher=NASAspaceflight |access-date=24 June 2017 }}</ref> The status of the first stage is unknown; it was not recovered because of problems with a nonfunctioning GPS tracking device. The rocket reached a final altitude of {{convert|289|km|mi|abbr=on}} and a final velocity of 5.1 km/s, compared to 7.5 km/s needed for orbit. |
The first launch attempt on 21 March 2007 was aborted at 00:05 GMT at the last second before launch and after the engine had ignited. It was, however, decided that another launch should be made the same day. The rocket successfully left the launch pad at 01:10 GMT on 21 March 2007 with a [[DemoSat]] payload for [[DARPA]] and [[NASA]]. The rocket performed well during the first-stage burn. However, during staging, the interstage fairing on the top of the first stage bumped the second-stage engine bell.<ref>{{cite web |url=http://www.spacedaily.com/reports/SpaceX_Confirms_Stage_Bump_On_Demoflight_2_999.html |title=SpaceX Confirms Stage Bump On Demoflight 2 |date=23 March 2007 |author=Greg Zsidisin |publisher=Space Daily |access-date=24 June 2017 }}</ref> The bump occurred as the second-stage nozzle exited the interstage, with the first stage rotating much faster than expected (a rotation rate of about 2.5°/s vs. expected rate of 0.5°/s maximum), thereby making contact with the [[niobium]] nozzle of the second stage. Elon Musk reported that the bump did not appear to have caused damage, and that the reason why they chose a niobium skirt instead of [[Reinforced carbon–carbon|carbon–carbon]] was to prevent problematic damage in the event of such incidents. Shortly after second-stage ignition, a stabilization ring detached from the engine bell as designed.<ref name="falconf2status">{{cite news |url=http://www.spaceflightnow.com/falcon/f2/status.html |title=Mission Status Center |date=20 March 2007 |publisher=Space Flight Now }}</ref> At around T+4:20, a circular coning oscillation began, which increased in amplitude until video was lost. At T+5:01, the vehicle started to roll, and telemetry ended. According to [[Elon Musk]], the second-stage engine shut down at T+7:30 because of a roll-control issue. Sloshing of propellant in the LOX tank increased oscillation. This oscillation would normally have been dampened by the Thrust Vector Control system in the second stage, but the bump to the second-stage nozzle during separation caused an overcompensation in the correction.<ref name="falconf2status"/> The rocket continued to within one minute of its desired location and also managed to deploy the satellite mass-simulator ring. While the webcast video ended prematurely, SpaceX was able to retrieve telemetry for the entire flight.<ref>{{cite web |url=https://www.nasaspaceflight.com/2007/03/falcon-i-flight-preliminary-assessment-positive-for-spacex/ |title=Falcon I flight – preliminary assessment positive for SpaceX |date=24 March 2007 |author=Chris Bergin |publisher=NASAspaceflight |access-date=24 June 2017 }}</ref> The status of the first stage is unknown; it was not recovered because of problems with a nonfunctioning GPS tracking device. The rocket reached a final altitude of {{convert|289|km|mi|abbr=on}} and a final velocity of 5.1 km/s, compared to 7.5 km/s needed for orbit. |
||
SpaceX characterized the test flight as a success, having [[Technology readiness level|flight-proven]] over 95% of Falcon 1's systems. Their primary objectives for this launch were to test responsive launch procedures and gather data.<ref name="demoflight_2_launch_update_12"/> The SpaceX team planned both a diagnosis and solution vetted by third-party experts, believing that the slosh issue could be corrected by adding baffles to the second-stage LOX tank and adjusting the control logic. Furthermore, the Merlin shutdown transient was to be addressed by initiating shutdown at a much lower thrust level, albeit at some risk to engine reusability. The SpaceX team wished to work on the problem to avoid a recurrence as they changed over into the operational phase for Falcon 1.<ref name="Space28">{{cite web |url=https://www.space.com/3615-spacex-declares-falcon-1-rocket-operational-perfect-test.html |title=SpaceX Declares Falcon 1 Rocket Operational Despite Less than Perfect Test |date=28 March 2007 |author=Brian Berger |publisher=Space.com |access-date=24 June 2017 }}</ref> |
SpaceX characterized the test flight as a success, having [[Technology readiness level|flight-proven]] over 95% of Falcon 1's systems. Their primary objectives for this launch were to test responsive launch procedures and gather data.<ref name="demoflight_2_launch_update_12"/> The SpaceX team planned both a diagnosis and solution vetted by third-party experts, believing that the slosh issue could be corrected by adding baffles to the second-stage LOX tank and adjusting the control logic. Furthermore, the Merlin shutdown transient was to be addressed by initiating shutdown at a much lower thrust level, albeit at some risk to engine reusability. The SpaceX team wished to work on the problem to avoid a recurrence as they changed over into the operational phase for Falcon 1.<ref name="Space28">{{cite web |url=https://www.space.com/3615-spacex-declares-falcon-1-rocket-operational-perfect-test.html |title=SpaceX Declares Falcon 1 Rocket Operational Despite Less than Perfect Test |date=28 March 2007 |author=Brian Berger |publisher=Space.com |access-date=24 June 2017 }}</ref> |
Revision as of 14:20, 29 September 2023
Function | Orbital launch vehicle |
---|---|
Manufacturer | SpaceX |
Country of origin | United States |
Project cost | US$90 million |
Cost per launch | US$7 million |
Size | |
Height | 21 m (69 ft) |
Diameter | 1.7 m (5.6 ft) |
Mass | 28 t (62,000 lb) |
Stages | 2 |
Capacity | |
Payload to LEO | |
Orbital inclination | 9.0 - 9.35° |
Mass | |
Payload to SSO | |
Mass | 200 kg (440 lb)[3] |
Launch history | |
Status | Retired[4] |
Launch sites | Omelek Island |
Total launches | 5 |
Success(es) | 2 |
Failure(s) | 3 |
Partial failure(s) | 0 |
First flight | 24 March 2006 22:30 GMT |
Last flight | 14 July 2009 03:35 GMT |
First stage | |
Powered by | 1 Merlin 1A (first 2 flights) 1 Merlin 1C (final 3 flights) |
Maximum thrust | 450 kN (100,000 lbf) |
Specific impulse | 255 s (2.50 km/s) (sea level) |
Burn time | 169 s |
Propellant | RP-1/LOX |
Second stage | |
Powered by | 1 Kestrel |
Maximum thrust | 31 kN (7,000 lbf) |
Specific impulse | 327 s (3.21 km/s) |
Burn time | 378 s |
Propellant | RP-1/LOX |
Part of a series on |
Private spaceflight |
---|
Active companies |
Active vehicles |
Contracts and programs |
Related |
Falcon 1 was a small-lift launch vehicle that was operated from 2006 to 2009[5] by SpaceX, an American aerospace manufacturer. On 28 September 2008, Falcon 1 became the first privately-developed fully liquid-fueled launch vehicle to go into orbit around the Earth.[6][7]: 203
The two-stage-to-orbit rocket used LOX/RP-1 for both stages, the first powered by a single Merlin engine and the second powered by a single Kestrel engine. It was designed by SpaceX from the ground up.
The vehicle was launched a total of five times. After three failed launch attempts, Falcon 1 achieved orbit on its fourth attempt in September 2008 with a mass simulator as a payload. On 14 July 2009, Falcon 1 made its second successful flight, delivering the Malaysian RazakSAT satellite to orbit on SpaceX's first commercial launch (fifth and final launch overall). Following this flight, the Falcon 1 was retired and succeeded by Falcon 9.
SpaceX had announced an enhanced variant, the Falcon 1e,[4] but development was stopped in favor of Falcon 9.
History
Private funding
The Falcon 1 rocket was developed with private funding.[8][9] The only other orbital launch vehicles to be privately funded and developed were the Conestoga in 1982; and Pegasus, first launched in 1990, which uses a large aircraft as its launch platform.[10]
The total development cost of Falcon 1 was approximately US$90 million[11] to US$100 million.[12]
While the development of Falcon 1 was privately funded, the first two Falcon 1 launches were purchased by the United States Department of Defense under a program that evaluates new US launch vehicles suitable for use by DARPA.[9][13][14]
Cancelled launches
As part of a US$15 million contract, Falcon 1 was to carry the TacSat-1[15] in 2005. By late May 2005, SpaceX stated that Falcon 1 was ready to launch TacSat-1 from Vandenberg. But the Air Force did not want the launch of an untested rocket to occur until the final Titan IV flew from nearby SLC 4E. Subsequent and repeated delays due to Falcon 1 launch failures delayed TacSat-1's launch. After TacSat-2 was launched on an Orbital Sciences Minotaur I on 16 December 2006, the Department of Defense re-evaluated the need for launching TacSat-1. In August 2007, the Department of Defense canceled the planned launch of TacSat-1[16] because all of the TacSat objectives had been met.
An August 2005 update on SpaceX's website showed 6 launches planned for Falcon 1, with customers including MDA Corp (CASSIOPE, which eventually launched in 2013 on Falcon 9), Swedish Space Corp and US Air Force.[17]
Design
According to SpaceX, the Falcon 1 was designed to minimize price per launch for low-Earth-orbit satellites, increase reliability, and optimize flight environment and time to launch.[18] It also was used to verify components and structural design concepts that would be reused in the Falcon 9. SpaceX started with the idea that the smallest useful orbital rocket was the minimum viable product (Falcon 1 with about 450 kg or 990 lb to orbit), instead of building something larger and more complicated, and then running out of money and going bankrupt.[19][citation needed]
First stage
The first stage was made from friction-stir-welded 2219 aluminum alloy.[20] It employs a common bulkhead between the LOX and RP-1 tanks, as well as flight pressure stabilization. It can be transported safely without pressurization (like the heavier Delta II isogrid design) but gains additional strength when pressurized for flight (like the Atlas II, which could not be transported unpressurized). The parachute system, built by Irvin Parachute Corporation, uses a high-speed drogue chute and a main chute.
For the first two launches, the Falcon 1 used a Merlin 1A engine. An improved version of the Merlin 1A, the Merlin 1B, was supposed to fly on later flights of the Falcon 1, although it was further improved to create the Merlin 1C, which was first flown on the third Falcon 1 flight, and on the first 5 flights of the Falcon 9. The Falcon 1 first stage was powered by a single pump-fed Merlin 1C engine burning RP-1 and liquid oxygen providing 410 kilonewtons (92,000 lbf) of sea-level thrust and a specific impulse of 245 s (vacuum Isp 290 s).[20] The first stage burns to depletion, taking around 169 seconds to do so.[20]
Second stage
The second stage Falcon 1 tanks were built with a cryogenic-compatible 2014 aluminum alloy,[20] with the plan to move to aluminum-lithium alloy on the Falcon 1e.[20] The helium pressurization system pumps propellant to the engine, supplies heated[20] pressurized gas for the attitude control thrusters, and is used for zero-g propellant accumulation prior to engine restart. The Kestrel engine includes a titanium heat exchanger to pass waste heat to the helium, thereby greatly extending its work capacity.[21] The pressure tanks are composite overwrapped pressure vessels made by Arde corporation with inconel alloy and are the same as those used in the Delta III.[22]
The second stage was powered by a pressure-fed Kestrel engine with 31 kilonewtons (7,000 lbf) of vacuum thrust and a vacuum specific impulse of 330 s.[20]
Reusability
The first stage was originally planned to return by parachute to a water landing and be recovered for reuse, but this capability was never demonstrated.[23][24] The second stage was not designed to be reusable.[23][24]
Launch sequence
At launch, the first stage engine (Merlin) is ignited and throttled to full power while the launcher is restrained and all systems are verified by the flight computer. If the systems are operating correctly, the rocket is released and clears the tower in about seven seconds. The first-stage burn lasts about 2 minutes and 49 seconds. Stage separation is accomplished with explosive bolts and a pneumatically actuated pusher system.[citation needed] The second stage Kestrel engine burns for about six minutes, inserting the payload into a low Earth orbit. It is capable of multiple restarts.[citation needed]
Pricing
SpaceX quoted Falcon 1 launch prices as being the same for all customers.[25] In 2005 Falcon 1 was advertised as costing $5.9 million ($7.3 million when adjusted for inflation in 2015).[1][26] In 2006 until 2007 the quoted price of the rocket when operational was $6.7 million.[27] In late 2009 SpaceX announced new prices for the Falcon 1 and 1e at $7 million and $8.5 million respectively, with small discounts available for multi-launch contracts,[18] and in 2012 announced that payloads originally selected as flying on the Falcon 1 and 1e would fly as secondary payloads on the Falcon 9.[4]
Historically, the Falcon 1 was originally planned to launch about 600 kilograms (1,300 lb) to low-Earth orbit for US$6,000,000 but later declined to approximately 420 kilograms (930 lb) as the price increased to approximately US$9,000,000. It was SpaceX's offering intended to open up the smallsat launch market to competition. The final version of the Falcon 1, the Falcon 1e,[28] was projected to provide approximately 1,000 kg (2,200 lb) for US$11 million.
Several years ago, SpaceX was going to open up the smallsat launch market with the Falcon 1, which originally was to launch about 600 kilograms to LEO for $6 million; the payload capacity later declined to about 420 kg (930 lb) as the price increased to around $9 million. Later, the Falcon 1e was to provide approximately 1,000 kg (2,200 lb) for $11 million, but the company withdrew the vehicle from the market, citing limited demand.[29]
Launch sites
All flights were launched from Kwajalein Atoll using the SpaceX launch facility on Omelek Island and range facilities of the Reagan Test Site.
Vandenberg AFB Space Launch Complex 3W was the original launch site for Falcon 1, but it was abandoned at the test-fire stage due to persistent schedule conflicts with adjacent launch pads.[30] Cape Canaveral Air Force Station Space Launch Complex 40 (the Falcon 9 pad) was considered for Falcon 1 launches but never developed before Falcon 1 was retired.[31]
Variants
Falcon 1 Versions[18][32][33] |
Merlin A; 2006–2007 |
Merlin C; 2007–2009 |
Falcon 1e (proposed) |
---|---|---|---|
Stage 1 | 1 × Merlin 1A | 1 × Merlin 1C | 1 × Merlin 1C |
Stage 2 | 1 × Kestrel | 1 × Kestrel | 1 × Kestrel |
Height (max; m) |
21.3 | 22.25 | 26.83 |
Diameter |
1.7 (5.57743 ft) | 1.7 (5.57743 ft) | 1.7 (5.57743 ft) |
Initial thrust (kN) |
318 (71489.2 lbf) | 343 (77109.5 lbf) | 454 (102063 |
Takeoff weight (tonnes) |
27.2 | 33.23 | 38.56 |
Fairing diameter (Inner; m) |
1.5 | 1.5 | 1.71 |
Payload (LEO 185 km; kg) |
420[34] | 470[35] (290 to polar) |
1,010[36] (430 to polar) |
Price (Mil. USD) |
6.7 | 7 | 10.9 |
minimal Price/kg (LEO 185 km; USD) |
~14,000 | ~14,000 | ~8400 (~20,000 to polar) |
Success ratio (successful/total) |
0/2 | 2/3 | — |
Launches
Falcon 1 made five launches. The first three failed, however the subsequent two flights were successful, the first successful launch making it the first privately funded and developed liquid-propellant rocket to reach orbit.[6]: 203 The fifth launch was its first commercial flight, and placed RazakSAT into low Earth orbit.[37]
Flight No. | Date / time (UTC) | Launch site | Payload | Payload mass | Orbit | Customers | Launch outcome | Launch video |
---|---|---|---|---|---|---|---|---|
1 | 24 March 2006, 22:30 | Omelek Island | FalconSAT-2 | 19.5 kg | LEO (Planned) | DARPA | Failure | [video 1] |
Engine failure at T+33 seconds. Loss of vehicle.[38] FalconSAT-2 landed in a storage shed near the launch site.[39] | ||||||||
2 | 21 March 2007, 01:10 | Omelek Island | DemoSat | LEO (Planned) | DARPA | Failure | [video 2] | |
Successful first-stage burn and transition to second stage, maximal altitude 289 km. Harmonic oscillation at T+5 minutes. Premature engine shutdown at T+7 min 30 s. Failed to reach orbit.[40] | ||||||||
3 | 3 August 2008, 03:34[41] | Omelek Island | Trailblazer PRESat NanoSail-D Explorers |
4 kg | LEO (Planned) | ORS NASA NASA Celestis[42] |
Failure | [video 3] |
Residual stage-1 thrust led to collision between stage 1 and stage 2.[43] | ||||||||
4 | 28 September 2008, 23:15[24][44] | Omelek Island | RatSat | 165 kg | LEO | SpaceX | Success[24] | [video 4] |
Initially scheduled for 23–25 Sep, carried dummy payload – mass simulator, 165 kg (originally intended to be RazakSAT). | ||||||||
5 | 14 July 2009, 03:35[45] | Omelek Island | RazakSAT | 180 kg | LEO | ATSB | Success[37] | [video 5] |
Malaysian satellite was the only commercial contract launch of Falcon 1. |
Date | Payload | Customers | Launch outcome |
---|---|---|---|
2010 | Falcon 1e maiden flight[42] | SpaceX | Not scheduled |
Was to be maiden flight of Falcon 1e configuration | |||
2010 | Not known | MDA Corp[46] | Not scheduled |
2010 | Not known | Swedish Space Corporation[46] | Not scheduled |
2011 | Not known | SpaceDev | Not scheduled |
2011–2014 | OG2 | Orbcomm[47] | Successful – Falcon 9 |
18 satellites, launch vehicle switched to Falcon 9. | |||
2013 | FORMOSAT-5 | NSPO | Successful – Falcon 9 |
Launch vehicle switched from Falcon 1e to Falcon 9. | |||
2014–2015 | Small satellites | Astrium | Not scheduled |
Launch vehicle was to be Falcon 1e. |
First flight
Launch sequence (maiden flight example); time scale is in seconds. |
The maiden flight of the Falcon 1 was postponed several times because of various technical issues with the new vehicle. Scheduling conflicts with a Titan IV launch at Vandenberg AFB also caused delays and resulted in the launch moving to the Reagan Test Site in the Kwajalein Atoll. The maiden launch was scheduled for 31 October 2005,[48] but was held off, then rescheduled for 25 November,[49] which also did not occur. Another attempt was made on 19 December 2005 but was scrubbed when a faulty valve caused a vacuum in the first stage fuel tank which sucked inward and caused structural damage. After replacing the first stage, Falcon 1 launched Saturday, 25 March 2006 at 09:30 local time. The DARPA payload was the United States Air Force Academy's FalconSAT–2, which would have measured space plasma phenomena.
The launch took place on Saturday, 24 March 2006 at 22:30 UTC, from the SpaceX launch site on Omelek Island in the Marshall Islands. It ended in failure less than a minute into the flight because of a fuel line leak and subsequent fire. The vehicle had a noticeable rolling motion after liftoff, as shown on the launch video, rocking back and forth a bit, and then at T+26 seconds rapidly pitched over. Impact occurred at T+41 seconds onto a dead reef about 250 feet from the launch site. The FalconSAT–2 payload separated from the booster and landed on the island, with damage reports varying from slight to significant.[50] SpaceX initially attributed the fire to an improperly tightened fuel-line nut. A later review by DARPA found that the nut was properly tightened, since its locking wire was still in place, but had failed because of corrosion from saltwater spray.
SpaceX implemented numerous changes to the rocket design and software to prevent this type of failure from recurring, including stainless steel to replace aluminum hardware (which is actually less expensive, although the trade off is being a little heavier in weight) and pre-liftoff computer checks that increased by a factor of thirty.[51][52]
Second flight
The second test flight was originally scheduled for January 2007, but was delayed because of problems with the second stage. Before the January launch date, SpaceX had stated earlier potential launch dates, moving from September 2006 to November and December. In December the launch was rescheduled for 9 March, but delayed because of range availability issues caused by a Minuteman III test flight, which would re-enter over Kwajelein. The launch attempt on 19 March was delayed 45 minutes from 23:00 GMT because of a data-relay issue, and then scrubbed 1 minute 2 seconds before launch at 23:45 because of a computer issue, whereby the safety computer incorrectly detected a transmission failure caused by a hardware delay of a few milliseconds in the process. 20 March attempt was delayed 65 minutes from an originally planned time of 23:00 because of a problem with communications between one of the NASA experiments in the payload and the TDRS system.
The first launch attempt on 21 March 2007 was aborted at 00:05 GMT at the last second before launch and after the engine had ignited. It was, however, decided that another launch should be made the same day. The rocket successfully left the launch pad at 01:10 GMT on 21 March 2007 with a DemoSat payload for DARPA and NASA. The rocket performed well during the first-stage burn. However, during staging, the interstage fairing on the top of the first stage bumped the second-stage engine bell.[53] The bump occurred as the second-stage nozzle exited the interstage, with the first stage rotating much faster than expected (a rotation rate of about 2.5°/s vs. expected rate of 0.5°/s maximum), thereby making contact with the niobium nozzle of the second stage. Elon Musk reported that the bump did not appear to have caused damage, and that the reason why they chose a niobium skirt instead of carbon–carbon was to prevent problematic damage in the event of such incidents. Shortly after second-stage ignition, a stabilization ring detached from the engine bell as designed.[54] At around T+4:20, a circular coning oscillation began, which increased in amplitude until video was lost. At T+5:01, the vehicle started to roll, and telemetry ended. According to Elon Musk, the second-stage engine shut down at T+7:30 because of a roll-control issue. Sloshing of propellant in the LOX tank increased oscillation. This oscillation would normally have been dampened by the Thrust Vector Control system in the second stage, but the bump to the second-stage nozzle during separation caused an overcompensation in the correction.[54] The rocket continued to within one minute of its desired location and also managed to deploy the satellite mass-simulator ring. While the webcast video ended prematurely, SpaceX was able to retrieve telemetry for the entire flight.[55] The status of the first stage is unknown; it was not recovered because of problems with a nonfunctioning GPS tracking device. The rocket reached a final altitude of 289 km (180 mi) and a final velocity of 5.1 km/s, compared to 7.5 km/s needed for orbit.
SpaceX characterized the test flight as a success, having flight-proven over 95% of Falcon 1's systems. Their primary objectives for this launch were to test responsive launch procedures and gather data.[40] The SpaceX team planned both a diagnosis and solution vetted by third-party experts, believing that the slosh issue could be corrected by adding baffles to the second-stage LOX tank and adjusting the control logic. Furthermore, the Merlin shutdown transient was to be addressed by initiating shutdown at a much lower thrust level, albeit at some risk to engine reusability. The SpaceX team wished to work on the problem to avoid a recurrence as they changed over into the operational phase for Falcon 1.[56]
Third flight
SpaceX attempted the third Falcon 1 launch on 3 August 2008 (GMT) from Kwajalein.[57] This flight carried the Trailblazer (Jumpstart-1) satellite for the US Air Force,[58] the NanoSail-D and PREsat nanosatellites for NASA and a space burial payload for Celestis.[59] The rocket did not reach orbit. However, the first stage, with the new Merlin 1C engine, performed perfectly.[60]
When preparing for launch, an earlier launch attempt was delayed by the unexpected slow loading of helium onto the Falcon 1; thus exposing the fuel and oxidizer to the cryogenic helium, rendering the vehicle in a premature launch state. Still within the specified window, the launch attempt was recycled, but aborted half a second before lift-off because of a sensor misreading. The problem was resolved, and the launch was again recycled. With 25 minutes left in the launch window, the Falcon 1 lifted off from Omelek Island at 03:35 UTC. During the launch, small vehicle roll oscillations were visible. Stage separation occurred as planned, but because residual fuel in the new Merlin 1C engine evaporated and provided transient thrust, the first stage recontacted the second stage, preventing successful completion of the mission.[61]
The SpaceX flight-3 mission summary indicated that flight 4 would take place as planned and that the failure of flight 3 did not make any technology upgrades necessary. A longer time between first-stage engine shutdown and stage separation was declared to be enough.[43] The full video of the third launch attempt was made public by SpaceX a few weeks after the launch.[62]
Musk blamed himself for the failure of this launch, as well as the two prior attempts, explaining at the 2017 International Astronautical Congress that his role as chief engineer in the early Falcon 1 launches was not by choice and almost bankrupted the company before succeeding:[63]
And the reason that I ended up being the chief engineer or chief designer, was not because I want to, it's because I couldn't hire anyone. Nobody good would join. So I ended up being that by default. And I messed up the first three launches. The first three launches failed. Fortunately the fourth launch which was – that was the last money that we had for Falcon 1 – the fourth launch worked, or that would have been it for SpaceX.
Musk further explained the situation to Ars Technica journalist Eric Berger:[64]
At the time I had to allocate a lot of capital to Tesla and SolarCity, so I was out of money. We had three failures under our belt. So it's pretty hard to go raise money. The recession is starting to hit. The Tesla financing round that we tried to raise that summer had failed. I got divorced. I didn't even have a house. My ex-wife had the house. So it was a shitty summer.
Fourth flight
Following the three prior failures, the SpaceX team assembled the fourth rocket using available parts in six weeks as a last chance for the company. A Boeing C-17 Globemaster III was chartered to quickly deliver the rocket, but along the way, the rocket partially imploded when depressurization exceeded what the SpaceX team had expected from the C-17's manual and the rocket had to undergo emergency repairs to be saved.[65] Despite the challenges, the fourth flight of the Falcon 1 rocket successfully flew on 28 September 2008, delivering a 165-kilogram (363-pound) non-functional boilerplate spacecraft into low Earth orbit.[44] It was Falcon 1's first successful launch and the first successful orbital launch of any privately funded and developed, fully liquid-propelled carrier rocket.[66]
The launch occurred from Omelek Island, part of the Kwajalein Atoll in the Marshall Islands.[67] Liftoff occurred at 23:15 UTC on 28 September 15 minutes into a 5-hour launch window. If the launch had been scrubbed, it could have been conducted during the same window until 1 October.[68] 9 minutes 31 seconds after launch, the second-stage engine shut down, after the vehicle reached orbit.[67] The initial orbit was reported to be about 330 × 650 km.[66] Following a coast period, the second stage restarted and performed a successful second burn, resulting in a final orbit of 621 × 643 km × 9.35°.
The rocket followed the same trajectory as the previous flight, which failed to place the Trailblazer, NanoSail-D, PRESat and Celestis Explorers spacecraft into orbit. No major changes were made to the rocket, other than increasing the time between first-stage burnout and second-stage separation. This minor change addressed the failure seen on the previous flight, recontact between the first and second stages, by dissipating residual thrust in the first-stage engine before separating them.[69][70][71]
Ratsat and the attached second stage are still in orbit as of 2021.[72]
Fifth flight
SpaceX announced that it had completed construction of the fifth Falcon 1 rocket and was transporting the vehicle to the Kwajalein Atoll launch complex where it was to be launched on 21 April 2009, which would be 20 April 2009 in the United States.[73] Less than a week before the scheduled launch date, Malaysian news reported that unsafe vibration levels had been detected in the rocket and repairs were expected to take about six weeks.[74] On 20 April 2009, SpaceX announced in a press release that the launch had been postponed because of a potential compatibility issue between the RazakSAT spacecraft and the Falcon 1 launch vehicle. A concern had been identified regarding the potential impact of predicted vehicle environments on the satellite.[75] On 1 June, SpaceX announced that the next launch window would open Monday, 13 July and extend through Tuesday, 14 July, with a daily window to open at 21:00 UTC (09:00 local time[76]).
The launch on Monday, 13 July was successful, placing RazakSAT into its initial parking orbit. Thirty-eight minutes later, the rocket's second-stage engine fired again to circularize the orbit. The payload was then successfully deployed.[77] After the launch Elon Musk, founder and CEO of SpaceX, told a reporter the launch had been a success. "We nailed the orbit to well within target parameters...pretty much a bullseye" Musk said.[77]
The Falcon 1 upper stage is still in low Earth orbit as of 2021.[78]
End of Program
Following the fifth flight, future launches of Falcon-1 were postponed, and eventually cancelled, and the vehicle decommissioned from service,[79] with SpaceX stating “We could not make Falcon 1 work as a business.”[80] Launches which had been booked onto Falcon-1 were moved to other vehicles or rebooked as Falcon-9 rideshare payloads.[80]
See also
- Comparison of orbital launch systems
- Comparison of orbital launchers families
- Falcon 1e
- Falcon 9
- Vega
- List of Vega launches
References
- ^ a b Highlights in Space 2005: Progress in Space Science, Technology and Applications, International Cooperation and Space Law. International Astronautical Federation, United Nations. Office for Outer Space Affairs, International Institute of Space Law. 1 January 2006. p. 11. ISBN 978-9211009897.
- ^ "SpaceX Falcon Data Sheet". Space Launch Report. Retrieved 21 April 2021.
- ^ "Users Guide" (PDF). www.georing.biz. Retrieved 11 March 2021.
- ^ a b c "Falcon 1". Space Exploration Technologies Corporation. Archived from the original on 18 January 2012. Retrieved 14 September 2010.
- ^ Engel, Max (1 March 2013). "Launch Market on Cusp of Change". Satellite Today. Archived from the original on 18 February 2013. Retrieved 15 February 2013.
SpaceX is not the first private company to try to break through the commercial space launch market. The company, however, appears to be the real thing. Privately funded, it had a vehicle before it got money from NASA, and while NASA's space station resupply funds are a tremendous boost, SpaceX would have existed without it.
- ^ a b Vance, Ashlee (2015). Elon Musk : Tesla, SpaceX, and the Quest for a Fantastic Future. New York: HarperCollins. ISBN 978-0-06-230123-9.
- ^ Tariq Malik (29 September 2008). "SpaceX Successfully Launches Falcon 1 Rocket Into Orbit". Space.com. Retrieved 6 April 2022.
- ^ Maney, Kevin (17 June 2005). "Private sector enticing public into final frontier". USAtoday.com.
- ^ a b Hoffman, Carl (22 May 2007). "Elon Musk Is Betting His Fortune on a Mission Beyond Earth's Orbit". Wired Magazine. Retrieved 14 March 2014.
- ^ "Orbital Marks 25th Anniversary Of Company's Founding". Orbital Sciences. Archived from the original on 17 May 2011. Retrieved 2 April 2007.
- ^
"Commercial Market Assessment for Crew and Cargo Systems" (PDF). nasa.gov. NASA. 27 April 2011. p. 40. Retrieved 10 June 2015.
SpaceX has publicly indicated that the development cost for Falcon 9 launch vehicle was approximately $300 million. Additionally, approximately $90 million was spent developing the Falcon 1 launch vehicle which did contribute to some extent to the Falcon 9, for a total of $390 million. NASA has verified these costs.
- ^ Berger, Eric (2021). Liftoff. William Morrow and Company. p. 215. ISBN 978-0-06-297997-1.
- ^ "Falcon 1 Reaches Space But Loses Control and is Destroyed on Re-Entry". Satnews.com. 21 March 2007. Archived from the original on 28 September 2007.
- ^ Graham Warwick and Guy Norris, "Blue Sky Thinking: DARPA at 50," Aviation Week & Space Technology, 18–25 Aug 2008, page 18.
- ^ "TacSat-1" (PDF). Responsivespace.com. Archived from the original (PDF) on 16 May 2006. Retrieved 18 August 2017.
- ^ "Report: Pentagon cancels TacSat-1 launch". spacetoday.net. 18 August 2007. Retrieved 15 July 2011.
- ^ Musk, Elon (20 December 2005). "June 2005 through September 2005 Update". SpaceX News. SpaceX. Archived from the original on 12 June 2019. Retrieved 14 November 2016.
- ^ a b c "Falcon 1 Overview". SpaceX. Archived from the original on 18 January 2012. Retrieved 5 May 2007.
- ^ Dead link: "YouTube". Youtube.com. Retrieved 18 August 2017.[dead YouTube link]
- ^ a b c d e f g Bjelde, Brian; Max Vozoff; Gwynne Shotwell (August 2007). "The Falcon 1 Launch Vehicle: Demonstration Flights, Status, Manifest, and Upgrade Path". 21st Annual AIAA/USU Conference on Small Satellites (SSC07 ‐ III ‐ 6). Retrieved 6 December 2013.
- ^ "Falcon 1 Flight Three Press Kit" (PDF). SpaceX. Archived from the original (PDF) on 1 October 2008. Retrieved 30 September 2008.
- ^ "Falcon 1". Encyclopedia Astronautica. Space Daily. Retrieved 25 November 2022.
- ^ a b Brown, Mary Beth (8 September 2005). "SpaceX Announces the Falcon 9 Fully Reusable Heavy Lift Launch Vehicle" (Press release). El Segundo, CA: SpaceX. Archived from the original on 26 March 2013. Retrieved 4 November 2009.
- ^ a b c d Clarke, Stephen (28 September 2008). "Sweet success at last for Falcon 1 rocket". Spaceflight Now. Retrieved 4 November 2009.
- ^ SpaceX, Falcon 1 Overview: Pricing and Performance Archived 18 January 2012 at the Wayback Machine (website viewed 31 August 2010)
- ^ "$5900000 in 2005 dollars". Wolfram Alpha. 12 August 2009.
- ^ Malik, Tariq (24 March 2006). "SpaceX's Inaugural Falcon 1 Rocket Lost Just After Launch". Space.com.
- ^ Jessy Xavier, "Europes First Vega Rocket Blasts Off Successfully Archived 2014-04-16 at the Wayback Machine," Oregon Herald, 13 February 2012
- ^
"Virgin Galactic relaunches its smallsat launch business". NewSpace Journal. 12 July 2012. Retrieved 11 July 2012.
Several years ago, SpaceX was going to open up the smallsat launch market with the Falcon 1, which originally was to launch about 600 kilograms to LEO for $6 million; the payload capacity later declined to about 420 kilograms as the price increased to around $9 million. Later, the Falcon 1e was to provide approximately 1,000 kilograms for $11 million, but the company withdrew the vehicle from the market, citing limited demand.
- ^ Berger, Brian (9 January 2006). "SpaceX To Try Again Feb. 9". Space News. Archived from the original on 8 March 2006.
- ^ Kelly, John (25 April 2007). "SpaceX cleared for Cape launches". Florida Today.
- ^ "SpaceX Falcon 1 Data Sheet" (PDF). SpaceX. 28 September 2008. Archived from the original (PDF) on 1 October 2008.
- ^ "Falcon 1 Users Guide" (PDF). SpaceX. 28 September 2008. Archived from the original (PDF) on 26 February 2009.
- ^ "Falcon-1 (Development Version)".
- ^ "Falcon-1".
- ^ "Users Guide" (PDF). www.georing.biz. Retrieved 11 March 2021.
- ^ a b Stephen Clarke (14 July 2009). "Commercial launch of SpaceX Falcon 1 rocket a success". Spaceflight Now. Retrieved 24 June 2017.
- ^ Tom Junod (14 November 2012). "Elon Musk: Triumph of His Will". Esquire. Retrieved 24 June 2017.
- ^ France, Marty; Lawrence, Tim. "FalconSAT-2 Launched (and Recovered)" (PDF). United States Air Force Academy. Archived (PDF) from the original on 21 September 2015. Retrieved 15 March 2013.
- ^ a b "Demo Flight 2 Flight Review Update" (PDF). SpaceX. 15 June 2007. Archived from the original (PDF) on 3 December 2008.
- ^ Stephen Clarke (3 August 2008). "Falcon 1 suffers another setback". Spaceflight Now. Retrieved 24 June 2017.
- ^ a b "Launch Manifest". SpaceX. Archived from the original on 14 April 2009. Retrieved 3 August 2008.
- ^ a b "Flight 3 mission summary". SpaceX. 6 August 2008. Archived from the original on 27 September 2018. Retrieved 24 June 2017.
- ^ a b "Flight 4 Launch Update". SpaceX. 23 September 2008. Archived from the original on 3 January 2010.
- ^ "SPACEX And ATSB Announce New Launch Date For Razaksat Satellite" (Press release). SpaceX. 1 June 2009. Archived from the original on 25 June 2009. Retrieved 2 June 2009.
- ^ a b "Overview" (PDF). www.nasa.gov. 17 June 2009. Retrieved 10 March 2021.
- ^ "ORBCOMM and SpaceX Reach Deal To Launch Satellite Constellation" (Press release). SpaceX. 3 September 2009. Archived from the original on 2 January 2010. Retrieved 3 September 2009.
- ^ SpaceX reveals Falcon 1 Halloween date, NASASpaceFlight.com, 10 October 2005, accessed 31 January 2019.
- ^ SPACEX set maiden flight – goals, NASASpaceFlight.com, 18 November 2005, accessed 31 January 2019.
- ^ Kimbal Musk (25 March 2006). "Someone's looking out for that satellite…". Kwajalein Atoll and Rockets. Retrieved 24 June 2017.
- ^ Brian Berger (19 July 2006). "Falcon 1 Failure Traced to a Busted Nut". space.com. Retrieved 24 June 2017.
- ^ "Demo flight two update". Space.com. 19 January 2007.
- ^ Greg Zsidisin (23 March 2007). "SpaceX Confirms Stage Bump On Demoflight 2". Space Daily. Retrieved 24 June 2017.
- ^ a b "Mission Status Center". Space Flight Now. 20 March 2007.
- ^ Chris Bergin (24 March 2007). "Falcon I flight – preliminary assessment positive for SpaceX". NASAspaceflight. Retrieved 24 June 2017.
- ^ Brian Berger (28 March 2007). "SpaceX Declares Falcon 1 Rocket Operational Despite Less than Perfect Test". Space.com. Retrieved 24 June 2017.
- ^ "Falcon 1 suffers another setback". SpaceflightNow.com. 3 August 2008. Retrieved 25 November 2022.
- ^ "SpaceX conducts static test firing of next Falcon 1 rocket". SpaceX. Archived from the original on 30 June 2008. Retrieved 26 June 2008.
- ^ "The Explorers Flight". Space Services Incorporated (Celestis). Archived from the original on 7 September 2008. Retrieved 5 June 2008.
- ^ "Falcon Launch Video and Message from Elon Musk – NASA Watch". Nasawatch.com. Retrieved 18 August 2017.[permanent dead link ]
- ^ "SpaceX Telecon on Falcon 1 Launch Failure". NASA Watch. 6 August 2008.
- ^ SpaceX. "Media Gallery". SpaceX. Retrieved 18 August 2017.
- ^ Elon Musk (28 September 2017), Making Life Multiplanetary | 2017 International Astronautical Congress, retrieved 28 November 2018
- ^ Berger, Eric (2021). Liftoff. William Morrow and Company. p. 182. ISBN 978-0-06-297997-1.
- ^ Berger, Eric (2021). Liftoff. William Morrow and Company. pp. 181–197. ISBN 978-0-06-297997-1.
- ^ a b
Clark, Stephen (28 September 2008). "Sweet Success at Last for Falcon 1 Rocket". Spaceflight Now. Retrieved 6 April 2011.
the first privately developed liquid-fueled rocket to successfully reach orbit
- ^ a b Ray, Justin (28 September 2008). "Mission Status Center". Spaceflight Now. Retrieved 28 September 2008.
- ^ Musk, Elon (27 September 2008). "Falcon 1 Flight 4". SpaceX. Archived from the original on 25 July 2011. Retrieved 28 September 2008.
- ^ Malik, Tariq; Berger, Brian (6 August 2008). "SpaceX Traces Third Rocket Failure to Timing Error". Space.com. Retrieved 28 September 2008.
- ^ Clark, Stephen (27 September 2008). "SpaceX to launch its fourth Falcon 1 rocket on Sunday". Spaceflight Now. Retrieved 28 September 2008.
- ^ Schwartz, John (29 September 2008). "Private Company Launches Its Rocket Into Orbit". The New York Times. ISSN 0362-4331. Retrieved 29 September 2008.
- ^ "Stuff in Space". stuffin.space. Retrieved 22 January 2021.
- ^ Musk, Elon (17 March 2009). "Flight 4 Launch Update". Updates. SpaceX. Archived from the original on 5 April 2020. Retrieved 23 September 2008.
- ^ "Launch of RazakSAT postponed". The Star. 18 April 2009. Archived from the original on 4 June 2011.
- ^ "Launch of RazakSAT postponed". SpaceX. 20 April 2009. Archived from the original on 5 April 2020. Retrieved 19 March 2007.
- ^ Doug Messier (2 June 2009). "SpaceX sets Falcon 1 Launch for July 13". Parabolic Arc. Retrieved 24 June 2017.
- ^ a b "Falcon Launch Report". Spaceflight Now.
- ^ "Stuff in Space". stuffin.space. Retrieved 22 January 2021.
- ^ Caleb Henry (10 August, 2016). "SpaceX’s Shotwell: Falcon 1 Will not Return", Via Satellite. Retrieved 10 Feb. 2022.
- ^ a b Jeff Foust (9 August, 2016). "SpaceX offers large rockets for small satellites", Space News. Retrieved 10 Feb. 2022.
- Videos
Further reading
- Ray, Justin (19 December 2005). "Damage puts first SpaceX rocket launch on hold". Spaceflight Now. Archived from the original on 23 June 2015. Retrieved 20 December 2005.
- "SpaceX rocket fails first flight". BBC News. 24 March 2006.